We can’t wait to open the doors of Tropicana Field on April 6, 2026 and bring fans back home! The recovery process following Hurricane Milton in October 2024 required patience and persistence, and we’re grateful for the support along the way. Now that the roof is secure, we’re in the final stretch and focused on preparing the ballpark for baseball UNDER THE ROOF!
Roof Complete, Field Work Moves Forward
The journey to complete the roof at Tropicana Field began long before the final panel was secured on November 21, 2025 — a milestone that marked a major step forward in an ambitious, global effort.
Worldwide Resources
The process started with the design of a specialized roofing material by the Serge Ferrari Group, a French industrial company known for advanced architectural fabrics. From there, production moved to Germany, where the base membrane took shape. The material, a translucent, Teflon-coated fiberglass fabric known as PTFE was carefully woven together. A similar version of this material was famously used in spacesuits that protected Apollo astronauts during their missions to the moon.
Once manufactured, the massive PTFE rolls were shipped from Germany to China. There, they were precisely cut into 24 individual panels, each weighing approximately 5,000 pounds. After fabrication was complete, the panels crossed the Atlantic aboard large shipping vessels and eventually arrived in St. Petersburg, Florida, ready for installation.
Specialized Installation
Installing the panels at Tropicana Field presented its own unique challenges. The ballpark’s iconic dome shape meant traditional equipment, like boom lifts, couldn’t reach the installation points. Instead, crew members relied on ropes and harnesses, carefully suspending themselves more than 200 feet above the field while cranes lifted the panels into position. Using a system of winches, the team then pulled and stretched each panel into place with precision.
Each panel installation required a continuous six-hour window of clear, stable weather. Conditions were closely monitored, and if lightning entered the area, work immediately stopped, and the process had to restart to ensure safety. Once a panel was laid, it took an additional six days of gradual adjustments and securing before it was fully set.
Creating the Playing Field
With the roof now complete, Tropicana Field is one step closer to returning to full playing conditions. The arrival of the ballpark’s dirt, formally known as the infield mix, marks the next phase. This engineered blend of sand, silt, and clay will soon serve as the foundation for the 2026 Tampa Bay Rays.